Access to Brown Street from East Exchange Street near the University of Akron campus will be closed for approximately four weeks beginning Monday, March 24. The construction work is part of the East Exchange Street improvement project, which is expected to be completed early in July.
From the west (downtown), the detour will:
Turn right at Grant Street, left at East Thornton Street, right or left on Brown Street.
From the east (university area), the detour will:
Turn left at Grant Street, left at East Thornton Street, right or left on Brown Street.

Access to all residences and businesses on Brown Street will be maintained from the south, according to a news release from the City of Akron.
Also beginning Monday, March 24, the sidewalks between Sumner and Allyn streets (just east of the McDonald’s on East Exchange Street) will be under construction for about two weeks — that part of the project is expected to be finished by the middle of April.
Pedestrian access to the businesses in the area will be maintained. Free parking is available on the side streets (Allyn and Sumner), and a parking garage for retail customers is available behind the businesses on East Exchange Street.

Contractors will then move east to complete the sidewalks between Allyn and Kling streets for the next two weeks, with work to finish by the end of April.
Access to Brown Street should be restored at the end of April.
Spicer Street access to close beginning of May
Access to Spicer Street from East Exchange Street will be closed for approximately four weeks starting in the beginning of May. The detour, the news release said, will be announced at a later date.
The East Exchange Street project includes “full improvements” between Arc Drive and Fountain Street (to the east of state Route 8) including new pavement, curbs, sidewalks, bike lanes, street lighting, traffic signals, water main replacement, sewer reconstruction and landscaping, the release stated.
“I know this construction has been difficult for some of our local businesses and University of Akron students,” said Akron Mayor Shammas Malik. “In the end, we will have a fully updated corridor along one of our main roadways and a critical part of the University of Akron campus that we can be proud of.”
Contractors will finish up aesthetic improvements such as street trees after roadway completion.